Moreton Road is the clearest example we have of the work this page is written for: several plots, 244 piles and a programme of about ten weeks. Our clients on schemes like it are developers, builders, groundworkers and structural engineers with drawings in hand.
On a multi-plot site the piling and the concrete have to be planned together. At Buckingham we did both, and the finished substructure was handed over as a platform ready for the superstructure to start.
For planning a programme, the range across our CFA work is 10 to 20 piles a day, and the diameter and depth of the piles decide where in that range a scheme falls.
Send the drawings, the plot layout and any ground investigation report you hold. We will list the pile type, the diameters, the quantities and the beam lengths, so the whole package can be read line by line.