CFA PilingThe Avenue
Chichester, West Sussex
- Completed
- November 2025
- Pile type
- 300mm CFA Piles
- Number of piles
- 38 pile positions
- Load
- 60kN per bearing pile
- Ground met
- Made Ground over Sand, Gravel & Flint over Chalk
- Time on site
- 5 weeks
Geovex pile and build foundations across East and West Sussex. The job we can show you in detail is on The Avenue in Chichester, where hard flint tested the drilling and the team changed its approach on site.

This page tells that job plainly, including what went wrong and how it was put right. It is one example: our family has over 20 years in piling, and the jobs on this page and across the site are a selection. Any of our three offices will take an enquiry for a Sussex site.
Regional Offices
The job was the foundation for a large rear extension to a house: a steel-framed structure on a piled raft slab. Twenty protected trees stood close to the works. Continuous flight auger piling was chosen as the most efficient method for the ground that was expected.
We installed 38 CFA piles at 300mm diameter, each founded in chalk and each carrying 60kN. Several bores collapsed in the upper layers at first. By drilling further into the chalk the bores lined themselves and held, and that technique was used on 11 production piles.
Six piles were drilled to practical refusal in the dense flint. Extra piles were added to make up for the reduced depths. Every pile had sonic integrity testing before the slab was poured.
The raft slab covers 116m² at 200mm thick, in C32/40 concrete with A393 mesh, over 225mm Cellcore void formers. Piling and foundations took about five weeks in all, and the job was delivered on budget.

CFA PilingChichester, West Sussex
Not every Sussex job needs a CFA rig. Mini piles carry up to 400kN each, which is enough for many houses, extensions and smaller commercial buildings. The rigs are compact, the ground protection mats are smaller and setup is faster.
For auger mini piling we can bore an open hole in stable clay, or pump concrete through the auger as we drill when the ground is wet or will not stand. Where the ground suits them, screw piles are another light option: steel shafts with helical plates, loaded the same day they go in. A short job such as a garden building can be piled and slabbed in about four days, as our Greywell job in Hampshire was.

Our services: Mini pilingCFA pilingSFA pilingSCD pilingScrew pilingFoundations
Our knowledge of Sussex ground on this page is the Chichester job and nothing wider. The pile design there was based on British Geological Survey data. It showed made ground over sand and gravel, with chalk at roughly 4 to 6m depth.
On site the ground was far harder than that suggested. Extremely hard flint deposits wore down two lead augers and all of the follower augers, and the tooling had to be repaired twice during the programme. The lesson is plain: desk data is a starting point. A ground investigation of the site itself tells the engineer more before the piling starts.

Our clients are builders, developers, groundworkers and engineers who have drawings. Multi-plot, commercial and multi-week schemes are what this page is for, and we take shorter jobs too.
Chichester is a fair example of how we work when a site does not behave. The design was based on the British Geological Survey data available. When the flint proved harder than the data suggested, we repaired the tooling, changed the drilling technique and added piles, and the job was still delivered.
Before any of that, we will tell you if piling is not needed, or if another method would serve you better. We explain the options and you decide.